Notes
Slide Show
Outline
1
Low Impact Development and Stormwater Management
2
Contents of Presentation
  • What Is Low Impact Development?
  • Why Do We Need Low Impact Development
  • What Are the Goals and Basic Principles of Low Impact Development
  • Examples of Low Impact BMPs
  • Low Impact Development Case Studies
3
Low Impact Development

  • An innovative, environmental approach to land development and stormwater management


4
Why Do  We Need Low Impact Development ?
  • Protect and Improve
    • Water Quality
    • Watershed Hydrology
    • Fish and Wildlife
  • Reduce Infrastructure Costs
  • Make Communities More Attractive






5
 
6
 
7
 
8
Low Impact Development Objectives
  • Reduce Effective Impervious Areas (the impervious areas that generates and contributes stormwater runoff to waterways)
  • Maximize Treatment and Infiltration of Stormwater
  • Maximize Evapotranspiration of Stormwater
9
Low Impact Development Planning Concepts
  • Maintain/Improve Site Hydrology
  • Think Small
  • Control Stormwater at the Source
  • Use Natural , Nonstructural Methods
  • Create Multifunctional Environment


  • Modified from  Prince George County, Maryland




10
A. Maintain/Improve Site Hydrology
  •        Goal: Try to Mimic and Improve Existing   Site Conditions
  • Try to maintain predevelopment hydrology
  • … peak flow
  • … volume
  • … time of concentration
  • improve aesthetics
  • provide recreational resources
11
A. Maintain/Improve Site Hydrology
  •               Identify Sensitive Areas
  •     streams/buffers        steep slopes
    •   floodplains               woodlands
    • wetlands                  permeable soils
12
A. Maintain/Improve Site Hydrology
  •         Protect Natural Conditions
  • retain/protect important natural features
  • produce least hydrologic impact
  • minimize site disturbance
13
A. Maintain/Improve Site Hydrology
  • Evaluate Site Layout Alternatives
  • to Reduce, Minimize and Disconnect
  • Impervious Areas
    • road layout and size
    •           cul-de-sacs
    • cluster development
    •           drainage swales
    • increased flow paths
    •           bioretention
    • infiltration
14
B.  Think small
  • Small Areas: Micro-Subbasins
  • Small Storm Events
  • Small BMPs
15
Control Stormwater
 at Source
  • Control Hydrologic Impacts at Source
  • Distribute Controls Throughout Site
      • use many small stormwater controls (BMPs – best management practices)
      • Do not use one large detention basin to manage stormwater




16
Use Natural,
Nonstructural Stormwater Management Methods
  • Maximize Natural Features
      • Swales            Buffers
      • Woodlands     Slopes
  • Minimize the Use of Storm Sewers and Large Detention Basins
17
E.  Create Multifunctional Environment
  • Design Multifunctional Systems
  • Example:  Bioretention System
      • rain interception
      • Wildlife habitat
      • runoff storage
      • filtration-pollutant removal
      • infiltration-groundwater recharge
      • aesthetics
18
 
19
 
20
Using Site Design, Natural Features and Hydrology to Implement Low Impact Development
  • Low Impact Development Site Planning Process
21
Low Impact Development
 Site Planning Process
  • Step 1  Identify Institutional and Regulatory        Constraints
  • Step 2  Analyze Existing Site Conditions
  • Step 3  Integrate Hydrology and Existing Site Conditions into Initial Design
  • Step 4  Develop Preliminary Site Layout Plan and Stormwater Management Plan
  • Step 5  Measure Soil Infiltration Rates
  • Step 6  Revise Site Plan and Stormwater Management Plan Based on Results of Soils Testing
  • Step 7  Compare Pre and Post Development    Hydrology
  • Step 8  Revise and Complete Low Impact          Development Site Plan




22
Step 1  Identify Institutional and  Regulatory Constraints
  • Conventional Regulations & Regulators
      • often inflexible
      • restrict innovative development
  • Need for Variances/Zoning Changes
      • road width
      • length of cul de sacs
      • minimum lot setbacks
      • cluster housing

23
Step 2  Analyze Existing Site Conditions
  • Identify Areas to Protect and Integrate into Stormwater Management Plan
      • Trees
      • Wetlands
      • Streams and ponds
      • Steep slopes
      • Good soils (A and B soils)


24
 
25
Step 2  Analyze Existing Site Conditions
  • Reduce Limits of Clearing and Grading
      • save trees
      • protect wetlands, ponds, and streams
      • minimize soil compaction – protect and maintain existing soil conditions
      • minimize construction easements and storage areas


26
Step 3  Integrate Hydrology
 into Initial Design
  • Main Goal: Mimic Predevelopment Hydrology
      • Runoff Volume
      • Peak Flow Rate
      • Time of Concentration


  • Maximize Retention of Natural Features
      • Slopes
      • Vegetation
      • Waterways
      • Trees


  • Minimize Storm Sewers and End-of-Pipe BMPs


27
 
28
Step 4  Develop Preliminary Site Layout Plan and BMPs
  • Place Houses & Roads on Poor Soils
  • Treat and Infiltrate Runoff on Good Soils
  • Minimize Directly Connected Impervious Areas
  • Modify/Increase Drainage Flow Paths


29
Minimize Directly Connected
 Impervious Areas
  • Disconnect Roof Drains
  • Direct Flow from Impervious Areas to Vegetated Areas or Infiltration Areas
  • Encourage Sheet Flow through Vegetated Areas
  • Break Up Flow Directions From Large Paved Areas
30
 Minimize Total Site Impervious Area
  • Alternative Road Layouts
  • Narrow Roads
  • Reduced Sidewalks
      • one side
      • none
  • Reduced On-Street Parking
  • Smaller Rooftops-single vs. multifloor homes
  • Smaller Driveways
31
 
32
 
33
 
34
 
35
 
36
 
37
 
38
Modify/Increase
Drainage Flow Paths
  • Maximize Overland Sheet Flow
  • Increase Flow Paths
  • Maximize Use of Open Swale Systems
  • Lengthen and Flatten Site and Lot Slopes
  • Minimize Use of Storm Sewers
39
Step 5 Measure Soil Infiltration Rates
  • At Proposed BMP Locations
  • At Multiple Depths… Based on Type of BMP Proposed
40
Soils Testing
  • Dig test pit with backhoe
    • Identify soil characteristics
    • Determine seasonal high groundwater level
  • Measure soil infiltration rates with approved methodology
    • Use Infiltrometer
    • Do Not Use Percolation (perc) Test for Most BMPs
41
Infiltrometer Vs. Perc Test
  • Use infiltrometers to measure downward infiltration of stormwater
  • Do  not use percolation tests to measure downward infiltration of stormwater
  • Use percolation test if proposed BMP will incorporate lateral and vertical movement of stormwater (Example: infiltration trench)
  • Some BMP manuals do not allow the use of percolation tests to measure stormwater infiltration
42
 
43
 
44
 
45
Step 7  Compare Pre and Post Development Hydrology
  • Quantify Pre and Post Development Hydrology
      • Runoff Volume
      • Peak Flow Rate
      • Time of Concentration
  • Determine Additional Level of Control Required
46
Step 7  Revise and Complete Low Impact Site Plan
  • Use Trial and Error Iterative Process to Meet Stormwater Management Requirements


  • If Necessary, Use Downstream/End-of-Treatment Control Techniques to Meet Requirements
  • …Constructed Wetlands
  • …Wet Ponds
  • …Infiltration Basins
  • …Naturalized Extended Detention Basins
47
Modified LID Planning Process

  • Step 1  Develop Preliminary Site Layout Plan
  • Step 3  Identify Potential BMP Locations
  • Step 4  Perform Infiltration Testing
  • BMP Locations
  • BMP Depths
  • Step 5  Integrate LID BMPs Into Site Plan
  • Step 6  Compare Pre and Post Development Hydrology
  • Step 7  Complete Low Impact Site Design
48
Low Impact Development
  • Hydrologic Analysis
49
Hydrologic Design Approach
  • Use Low Impact Design to
    • Reduce runoff volume and peak flow
    • Maintain/increase flow time (Tc)
  • Use Low Impact BMPs to
    • Infiltrate and evaporate stormwater runoff
    • Treat stormwater runoff
  • Use Detention/Retention to
    • Meet final requirements


50
Stormwater Credits Can Be Used To Reduce Detention/Retention Needs
  • Natural Area Conservation
  • Disconnection of Rooftop Runoff
  • Disconnection of Other Runoff
  • Sheet Flow to Buffers
  • Use of Open Channels
  • Environmentally Sensitive Development
51
Low Impact Development
Best Management Practices (BMPs)

(Stormwater Controls)
52
Common Low Impact Development BMPs
  • Disconnectivity
  • Bioretention
  • Infiltration Systems
  • Open Swales
  • Permeable
    and Porous Pavements


53
 
54
 
55
Bioinfiltration Area – infiltrates stormwater
56
Biofiltration Area – filters stormwater
57
 
58
 
59
 
60
 
61
 
62
 
63
 
64
 
65
 
66
 
67
 
68
 
69
 
70
 
71
 
72
Soil Amendment
73

Rain  Barrels, Cisterns and Storage Tanks
74
 
75
 
76
 
77
BMP Selection Criteria
  • Goals
  • Physical Constraints
  • Regulatory Constraints
  • Public Acceptance
  • Costs
  • Schedule
78
BMP Selection - Goals
  • Peak Runoff Control
  • Runoff Volume Control
  • Water Quality
      • Nutrients
      • Bacteria
      • Metals
  • Flood Control
79
BMP Selection – Physical Constraints
  • Available Land
  • Soils
  • Slopes
  • Vegetation
  • Wetlands
  • Sensitive Areas
80
BMP Selection – Regulatory Constraints
  • Ordinances
      • Zoning
      • Subdivision
      • Stormwater Management
  • Regulations and Regulators
  • Design Criteria
81
BMP Selection – Public Acceptance Issues
  • Health Issues
      • Wetlands – West Nile disease
  • Aesthetics
  • Public Perception
  • American Dream House
82
BMP Selection - Costs
  • Construction Costs
  • Maintenance Costs
  • Loss of Income – Less units
  • Increased Income – higher house prices
83
BMP Selection – Scheduling Issues
  • Approvals & Permitting
  • Public Acceptance
  • Installation Constraints
    • wetlands
    • bioengineering
84
 
85
 
86
 
87
 
88
 
89
 
90
 
91
Medium Density
Residential Site
92
Medium Density
Residential Site
93
Medium Density
Residential Site
94
Medium Density
Residential Site
95
Conventional
Development
96
 
97
Construction Cost Comparison
98
Florida Aquarium LID Retrofit
99
 
100
 
101
 
102
 
103
 
104
 
105
 
106
 
107
Seattle Streets
 LID Program includes:
  • Bioretention – Rain Gardens
  • Natural Swales
  • Narrow Streets



108
 
109
 
110
 
111
 
112
F. X. Browne, Inc Low Impact Design Project LID Design
  • Pennsylvania Age Qualified Community
  • 209 Townhouses
  • Clubhouse and Day Spa
  • C and D Soils on Site
  • Forested With Mild Slopes
  • Intermittent Stream Runs Through Site
  • Goal: Infiltrate 2-Year Storm
113
 
114
F. X. Browne, Inc. Approach
  • Identify Potential BMPs
    • Locations
    • Depths
  • Perform Soil Testing
  • Evaluate Soil Data & BMPs
  • Develop Conceptual Plan
  • Develop Final Plan
115
List of Potential BMPs
  • Rooftop Disconnection
  • Grass Swales
  • Riparian Buffers
  • Bioinfiltration Systems
  • Infiltration Trenches
  • Infiltration Basins
  • Porous Pavement
  • Constructed Wetlands


116
 
117
 
118
Final F. X. Browne, Inc. Low Impact Development Plan
  • Rooftop Disconnection (90% of houses)
  • Riparian Buffers Along Stream
  • 10 Bioinfiltration Systems
  • 5 Infiltration Basins
  • 2 Constructed Wetlands
119
 
120
 
121
 
122
 
123
 
124
 
125
Low Impact Development
  • Grass swales
  • Bioretention systems – rain gardens
  • Grassed cul-de-sac islands
  • Lakes, ponds and wetlands
  • Vegetated riparian buffers
  • Natural prairie lawns
  • Narrow streets
  • Cluster development
  • Lots of open space


126
 
127
 
128
 
129
 
130
 
131
 
132
 
133
Other F. X. Browne, Inc.
Low Impact Development – Conservation Design Projects
134
 
135
 
136
 
137
 
138
Non-Structural Approaches to Stormwater Management
139
Environmental Ordinances
  • Zoning
  • Riparian Buffer
  • Stormwater Management
140
Zoning Ordinance
  • Setbacks and Yard Lines
  • Cluster Housing
  • Road Widths
  • Cul de Sac Lengths
  • Curb and Gutter
  • Detention Requirements
141
Riparian Buffer Ordinance
Benefits
  • Water Quality Protection
  • Stormwater Treatment & Infiltration
  • Habitat Improvement
  • Flood Control
  • Recreation
  • Aesthetics


142
 
143
Stormwater Management Ordinance
  • Meet Requirements of New DEP BMP Manual:
    • Peak Rate Control Standard
    • Volume Control Standard
    • Water Quality Control Standard
144
Summary: Low Impact Development
  • Low Impact Development is Feasible
  • Low Impact Development is Needed to Meet NPDES Stormwater Requirements
  • There is a need to:
  • Work with Municipal Officials/Engineers
  • Think “Outside of the Box”
  • Be Creative
  • Take Chances
145
Green Roofs
146
Types of Green Roofs
  • Intensive (traditional roof garden)
    • Minimum 1 foot soil depth
    • 80-150 lbs/sf
    • $25-40/sf
  • Extensive (environmental roof)
    • 1 to 5” of ‘soil’
    • 15-50 lbs/sf
    • $15-25/sf
147
 
148
 
149
 
150
 
151
 
152
 
153
Extensive Green Roofs
  • Slopes to 30%...need grids for slopes >20%
  • Best slope: 5 to 20%
  • Saturated weight: 10 to 50 lbs/sf
  • Alpine plants/succulents/low growing plants
154
Benefits of Green Roofs
  • Reduce city “heat island” effect
  • Reduce carbon dioxide  impact
  • Reduce summer air conditioning cost
  • Reduce winter heat demand
  • Potentially lengthen roof life 2 to 3 times
  • Treat nitrogen pollution in rain
  • Negate acid rain effect
  • Help reduce volume and peak rates of stormwater
  • Improve water quality of stormwater
  • Improve aesthetics


155
 
156
 
157
Vegetated Roof LID
 Fencing Academy of Philadelphia
158
 
159
 
160
 
161
Conclusion
  • Green roofs are an effective way to treat stormwater and reduce the volume of stormwater runoff
  • Green roofs are cost effective over the typical life of a building
  • Green roofs reduce heating and air conditioning costs
  • Green roofs have many additional benefits including cleaning the air and producing oxygen